75 Free Sample Questions related to the PMP exam after 30 June 2009 (PMBOK® Guide 4th Edition)

“If money is your hope for independence you will never have it. The only real security that a man will have in this world is a reserve of knowledge, experience, and ability.”

Henry Ford

Explanations

I want to skip the explanations section and go down to the test right now

Feedback

Mailed August 25 2008 by Aarti S. (USA): "Your tips and practice exams were really helpful and I was able to focus on areas that I was weak at and pass the exam.."
Mailed October 17 2007 by Tony C. (Japan): "Thanks, passed the PMP with 67%.  Almost exactly as on your 75 question practice test."
Mailed October 10 2007 by Naji C. (Canada): "I am glad that I did your tests online, the free 75q and the 175 one. The questions helped me pass the exam and really find gaps in my knowledge. By the way, you are the only one who covered the PTA questions. I had on my exam 3 PTA related questions."
Mailed October 10 2007 by Stefano B. (Italy): "I would like to thank you again for the free and precious support provided by your tests. They were really close to the exam and helped much me and my other 2 colleagues to pass the PMP exam with a good score."
Mailed July 14 2007 by Belinda C. (USA): "I did take the exam and passed it back in May. I believe that your questions were the closest to prep for the exam."
Mailed March 15 2007 by Dorin V. (Canada): "The sample test was very useful in evaluating my knowledge prior to the exam and deciding when I was really ready for it. I passed the exam on my first attempt with roughly the same percentage as the sample test. Thank you."
Mailed March 8 2007 by Pam H. (USA): "I only whish I could have found you earlier. I missed this exam 3 times. I even went through #######'s Boot Camp... a good course but something went amiss for me when I really saw the questions on the test ... I have not been studying these type of questions given to me from the Boot Camp."

Mailed January 8 2007 by Joseph K. (UK): "I did the test and had 54 correct answers. I then passed the exam. Your questions were a good preparation for the real thing. "

Mailed September 12 2006 by Claudia D. (USA): "I just took (and passed) the PMP exam yesterday. Your test is the closest I have found to the real thing. I was getting fairly high scores from other practice tests and was quite shocked yesterday by how difficult the real exam was."

Mailed May 9 2006 by Rick M. (USA): "I teach an 8 day PMP Prep Course. I have had over 120 of my students pass the PMP exam over the past 2 years. I have always encouraged my students to take your exam to test their knowledge."

Mailed April 20 2006 by Walid T. (Canada): "I found some of the questions quite challenging and requiring more than the allocated 72 seconds to answer ... the sample test provided a good learning experience."

Mailed January 25 2006 by John C. (USA): "Your test questions are very useful and helped me assessing where I need to do more."

Mailed August 1 2005 by Stephen L. (New Zealand): "Good questions."

Mailed June 14 2005 by Saurabh V. (India): "The test is the most comprehensive one that I have seen so far."

Mailed January 5 2005 by Bob H. (USA): "I passed with an 80%. Your site was quite helpful and a good benchmark. Thanks!"

Mailed August 26 2004 by David S. (UK): "I can start breathing again, score for the exam 158/200, thanks for the confidence boost from your test questions!"

Mailed June 29 2004 by Nadja V. (Finland): "I took several practice exams. Your exam provided the best reality check both in terms of level of difficulty of the actual PMP exam and my score on the final exam. Thanks."

Mailed Jan 12 2004 by Andrea I. (Italy): "I did the test two days before the exam and found it useful and also a good approximation of the real exam question, compared with other sample tests taken before. Moreover, the result reached was exactly the same as in the exam (84%)."

Mailed May 05 2003 by Dana P.B. (USA): "I did find the questions helpful. To the extent that I passed the exam on my first attempt."

Each question in this self assessment test has one best answer.
Time to finish the test: 90 Minutes.

There is a timer in the title bar (top of most browsers).

Click the dark blue button (below) to reset the timer to 00:00:00.
This sample test has been designed to help you practicing for the current PMP® exam—based on the PMBOK® Guide 4th Edition.
It is also helpful in preparation for other project management exams including PMI's CAPM® and PgMP® or CompTIA's Project+.
The passing score (the number of right answers to pass this preparation test) is 75%.
Please visit www.pmi.org and navigate to


to find more information about the PMP exam.
Visit the author at
-
www.oliverlehmann.com (English) or
-
www.oliverlehmann-training.de (German)
Click here for over 2,000 more prep questions from various providers.
PMI® did not participate in the development of this self assessment test and has not reviewed the content.
See references
Marked for review
  1. ________ is typically not referred to as a buffer type in Critical Chain project management.
 
Resource buffer
Free buffer
Feeding buffer
Project buffer

See references
Marked for review
  2. A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000.
  1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.
     
  2. The second project would be the development of a new product which could produce the following net profits after the end of the project:
1. year:       $ 15,000
2. year: $ 125,000
3. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the first 3 years, what is true?
 

Both projects are equally attractive.
The first project is more attractive by app. 7%.
The second project is more attractive by app. 5%.
The first project is more attractive by app. 3%.

See references
Marked for review
  3. A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?
 

The process is under control. It should not be adjusted.
A special cause should be investigated, the process should be adjusted.
The control limits should be adjusted.
The measuring equipment should be recalibrated.

See references
Marked for review
  4. Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives.

Which stage of team development can be difficult to overcome in such a situation?
 
Storming from Forming, Storming, Norming, Performing
Panic from Enthusiasm, Panic, Hope, Solution
Kickoff from Assignment, Kickoff, Training, Communicating
Frustration from Direction, Frustration, Cooperation, Collaboration

See references
Marked for review
  5. During a project Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000
CV: +100,000; SV: +120,000
CV: -100,000; SV: -120,000
CV: -120,000; SV: -100,000

See references
Marked for review
  6. A project manager spent some days to create a multi-page document which he called Project charter. The document should have been issued by the project sponsor. The sponsor found the document outsized and asked for a condensed document. 

Which of the following is not normally an element of the Project charter?

The authority level of the project manager
Detailed control account and work package descriptions
The business need that the project was undertaken to address
High-level risks

See references
Marked for review
  7. A document called ____________ is created by decomposing the project scope into smaller, more manageable elements.
 
Scope Statement
Network Logic Diagram
Work Breakdown Structure
Requested Change

See references
Marked for review
  8.

Which of the following tools is used to create a Risk Management Plan?

Risk planning meetings
Documentation reviews
Data precision rankings
Diagramming techniques

See references
Marked for review
  9. In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members and another one which was planned to begin in four weeks time with another five team members.

Which of the following activities should you do first?
 

Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2.
Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptness.
Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performance.
Restructure your team and delegate tasks in order to ensure the flow of communications in a team with the number of communication channels increased by a factor of 4.5.

See references
Marked for review
  10. A project manager needs a certain number of identical valve housings for a power station project.

He starts with 100 raw items which are made as metal castings. Out of this batch, 15 are found leaking from micro-porosities in a subsequent pressure test. 6 of these housings can be recovered by a special sealing process for raw castings.

The 91 housings are then being machined. After this process step 10 machined castings are found leaking. 3 of these items can also be saved using another sealing process for machined castings.

The remaining 84 housings are getting mounted to the power plant pipe work. During a pressure test after this process step it is found that 12 valves are leaking. Out of these a number of 6 valves can be saved by replacing the sealing rings used.

Finally the project manager has 78 valves which he can use. What is true?
 

RTY = 0.84

RTY = 0.78
RTY = 0.91
RTY = 0.65

See references
Marked for review
  11.

 You found the following Earned Value Analysis information for a recently closed out project:

SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
The project's deliverables have all been finished. The project came in on schedule but over budget.

See references
Marked for review
 12.

Which should be included in a Requirements management plan?

The document should trace requirements to project scope / WBS deliverables.

It should describe how requirements activities will be planned, tracked, and reported.

It should trace high-level requirements to more detailed requirements.

It should trace requirements to business needs, opportunities, goals, and objectives.

See references
Marked for review
 13. In a traditionally drawn decision tree, a circle represents ___________.                               
 
a chance to which no Expected Monetary Value can be assigned so that a likely pay-off can not be shown.
a decision to which no Expected Monetary Value can be assigned so that a likely pay-off can not be shown.
a chance to which an Expected Monetary Value may be assigned to calculate the most likely pay-off.
a decision to which an Expected Monetary Value may be assigned to calculate the most likely pay-off.

See references
Marked for review
 14.

A project management team has subcontracted work to a service company. Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project?

Quality audit
Deliverable inspection
Fixed price contract
Service level agreement

See references
Marked for review
 15. With your team you are using judgment from subject matter experts to identify and analyze project risks. There is a small number of experts available, but some of them have long been in a teacher-student or manager-assistant relationship.

Which of the following techniques can ensure best that there is no dominating opinion during an expert review?
 

Peer review

SWOT analysis

Delphi technique

Monetary value calculation

See references
Marked for review
 16. You are running a project for a customer based on a cost reimbursable contract with the following terms:
 
Target costs:     $ 1,000,000
Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= Point of total assumption, Break point) of the project?
 

$1,300,000
$1,500,000
$80,000
$1,125,000

See references
Marked for review
 17. During execution of a project which is performed for a customer on a T&M (Time and Material) contract base, a new project manager is taking over the assignment. 

He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. 

What should the project manager do?

Try to find some productive work for these staff members in the project and leave them on the team.
The best thing is to do nothing. The customer will not realize the problem anyway.
Try to find a responsible person for the over-assignment who can be made accountable.
Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.

See references
Marked for review
 18. In the following network logic diagram start dates are defined as early morning, finish dates are evening.

If tasks are scheduled to begin at early start date, what is true?


Activity B has a free float of 10 d.
Activity B has a total float of 10 d.
Activity A has a free float of 10 d.
Activity A has a total float of 10 d.

See references
Marked for review
 19. Your project is executed with a globally spread virtual team. The project progress has been found to be too slow. Which measure is most likely to immediately speed up the project?
 
Technical training for all team members
Daily phone conferences and detailed reporting
A team meeting at a location convenient to all team members
Collocation of team members at a suitable place

See references
Marked for review
 20.

A project management team wants to procure some customized products which are available in identical grade and quality from many vendors. What should be included in the procurement package to ensure that their offers will be comparable?
 

A statement of work describing the needs of the project in sufficient detail to enable vendors to make suitable proposals

A statement of work specifying attributes and metrics of the requested deliverables in detail to allow vendors submission of bids

The approved project scope statement, the WBS which should be broken down to Work Package level and the WBS dictionary

The risk management plan and the reports from those risk management reviews which have been made so far

See references
Marked for review
 21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering
Communication planning
Formal procurements closure
Network diagramming

See references
Marked for review
 22. You are assigned as the project manager to a project which is executed for a customer under FP contract. Your customer informed you this morning that they insist on certain "refinements" of the project scope.

You agree that the requested actions make really sense to the project, but believe that they constitute a major change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and working hours spent by yourself and the team on the implementation of the change and invoice these to the customer at appropriate rates.
Perform Earned Value Analysis to assess the current status of the project and get all the numbers you need to communicate the case to the Change Control Board which then will have to make the best decision regarding the customer request.
Check the contract, the project charter, the scope statement and other documents related to the project and the contract. Implement ADR (Alternative Dispute Resolution) procedures if the conflict cannot be resolved otherwise.
Talk to the project sales department and find a joint solution with them how to best reject the request considering the commercial and strategic value of the customer to the organization you are working for.

See references
Marked for review
 23. During a project the scope of a product purchased on a cost reimbursable contract has increased. The contract defines a fixed fee to cover the contractor‘s indirect costs and allow a profit. What is most likely to be true?
 
The contractor‘s indirect costs will increase and the customer‘s payment for them will increase, too.
The contractor‘s indirect costs will increase but the customer‘s payment for them will not increase.
The contractor‘s indirect costs will not increase but the customer‘s payment for them will.
Neither the contractor's indirect costs nor the customer‘s payment for them will increase.

See references
Marked for review
 24. A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality. Which of the following statements is not true?
 
Normal process variation is attributable to random causes and sometimes also called "white noise".
Special causes are easier to predict and handle than random causes (also called common causes).
Special causes are unusual events which are difficult to foresee and mostly produce outliers.
A process can be optimized to limit the bandwidth of variations due to random causes.

See references
Marked for review
 25. You are performing a project management audit in your company and find that most of the project plans are neither consistent nor up-to-date.

Which of the following statements is not true?

Projects should never be executed without a valid, updated and working project management plan.
The consistency of the project management plan is secondary because it is only the results that matter.
A great deal of effort is required to develop and update a project plan, but the benefits include less pressure on all stakeholders and a resulting product that will satisfy the requirements.
Poor planning and insufficient updating of project management plans are common reasons for cost and time overruns.

See references
Marked for review
 26. You want to perform active risk acceptance. What should you do?
 
Create contingency reserves in resources, money and time.
Develop a plan to minimize impact in case that an identified risk occurs.
Develop a plan to minimize the probability of occurrence for identified risks.
Make additional resources available to speed up the project.

See references
Marked for review
 27. A project manager made 3-point estimates on a critical path and found the following results:

Assuming ±3 Sigma precision level for each estimate, what is the standard deviation of the allover path?
 
App. 4.2 days
App. 5.2 days
App. 6.2 days
You can not derive the path standard deviation from the information given.

See references
Marked for review
 28.

When do bidder conferences normally take place?
 

After the contract has been awarded to keep alternatives open.
After submittal of bid or proposal, but before contract award.
Prior to the submittal of a bid or proposal by the bidder.
After technical meetings with bidders to discuss contract requirements.

See references
Marked for review
 29. What is defined by control limits?
 
A measuring instrument solely used to describe process capability. The process is found capable if the ±3 Sigma range is exceeded by not more than 0.3% of a tested sample lot.
The limits of the six Sigma area on either side of a control chart to plot measured values; data found outside the area are out of specification and can lead to rejection of an entire batch.
The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in quality assurance

See references
Marked for review
 30.

The Scope baseline consists of what?

Scope statement, WBS, and WBS dictionary
Cost baseline, Quality baseline and Schedule baseline
Configuration management plan and Configuration identification document
Procurement statement of work and Project scope statement

See references
Marked for review
 31. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6 days.

What is the minimum total duration between the Milestones A and B?

36 days
37 days
39 days
42 days

See references
Marked for review
 32.

Which tool and technique is used to Create WBS and Define activities?
 

Nominal group technique
Human resource assignment
Brainstorming
Decomposition

See references
Marked for review
 33. Which of the following statement(s) regarding whistle-blowing is/are not true?
  1. It is a term used to define an employee’s decision to disclose information on unethical, immoral or illegal actions at work to an authority figure.
  2. An employee should always discuss the matter with people external to the company before following the "chain of command" and discuss it with the immediate superior.
  3. The consequences of whistle-blowing are often extreme and include possible being branded as having bad judgment, firing, civil action and imprisonment.
  4. Carefully considered whistle-blowing can lead to the end of unethical business practices.
a
b
b, c
c, d

See references
Marked for review
 34. Which of the following statements is not true?
 
Attribute sampling is the process of assessing whether results conform to specifications or not.
Prevention means keeping errors out of the process by applying actions before the process starts changing its input.
Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer instead of as a means of process control.

See references
Marked for review
 35. Which statement describes best why you should document assumptions?
 
Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk identification.
Assumptions limit the project management team's options for decision making because they can not be controlled by the team.
In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.

See references
Marked for review
 36. Which is normally not regarded as an element of Cost of quality?
 
Prevention costs
Maintenance cost
Appraisal costs
Failure costs

See references
Marked for review
 37. You have recently been assigned as a project manager to a new B-O-T (Build, Operate, Transfer) capital project. Reviewing the initial documentation you found out that it has been calculated with a very small margin during operations of its product for the shareholders. What should you do?
 
As you are not responsible for lifecycle costing, you don't have to worry about operation profits. Focus on project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and modules - potentially from a big number of different suppliers - and integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk management processes. Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and accountability to shareholders with the person.

See references
Marked for review
 38. A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true?
 
The performing organization is a weak matrix.
The performing organization is doing "management by projects".
The performing organization is a strong matrix.
The performing organization is projectized.

See references
Marked for review
 39. You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences?
 
Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project.
When you are about to form a team for your project, keep in mind that some cultures are developed, others are more primitive. Some have values, some not. You should consequently avoid choosing members from countries with cultures that are not similar to your own.
Cultural dilemmas can prevent any project from being successful. They should therefore be smoothed or suppressed so as to make sure that they cannot disrupt project work. Your effort should concentrate on communication that can help reach that goal.
As norms regarding communication habits differ significantly across various cultures, communicating between people from different countries should only be done using language. The nonverbal dimension simply bears too many risks.

See references
Marked for review
 40. Which statement on conflicts is true?
Conflict resolution should focus on people, not issues.
Conflict is natural and forces a search for alternatives.
Conflict should always be handled in private and not in the team.
Too much openness is a common cause of conflict.

See references
Marked for review
 41. A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that it nevertheless has been implemented by the team members, who knew of the change request, but not of the rejection.

In order to avoid such a situation, Rejected change requests should be consistently communicated to stakeholders through which process?

Report performance
Verify scope
Perform integrated change control
Monitor and control risks

See references
Marked for review
 42. What is a trigger in project risk management? 
 
An expected situation causing an unidentified risk to occur
A warning sign that a previously identified risk might be occurring or has occurred
An unexpected situation causing an identified risk to occur
An unexpected situation causing an unidentified risk to occur

See references
Marked for review
 43. According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow.

You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks.

What should you do right now?

You should delay the payment also for 2 weeks.
You must immediately find a different contractor.
You should conduct a meeting with the contractor to resolve the delivery issues before making the payment.
You should make the payment and reschedule the project plan. 

See references
Marked for review
 44. In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources.

What is the term commonly used for this situation?

Concurrent engineering
Resource over-allocation
Resource pooling
Program management

See references
Marked for review
 45. What does the acronym RACI commonly stand for in project management?
 
Responsible, Accountable, to be Consulted, to be Informed
Remote, Attached, Connected, Integrated
Risk Analysis and Caution Initiative
Randomly Accessible Cashflow Information

See references
Marked for review
 46. You have used estimates made by your team members and applied the Critical path method to compute a Network logic diagram for your project. Then you found out that it cannot be sufficiently optimized for scarce resources and fast progress towards a given deadline. What should you do next?
 
Apply resource leveling heuristics to uncritical activities only.
Reduce estimates on duration and work efforts by an adequate percentage.
Apply Three-point estimation and Critical chain project management.
Remove physical constraints and replace hard logic with soft logic.

See references
Marked for review
 47. Liquidated damages (LDs) are contractually agreed payments in order to...
...give the contractor an incentive to meet an aggressive schedule or challenging quality objectives.
...penalize the contractor for late completion of a project or failure to meet specifications.
...cover the customer's costs caused by late completion or failure to meet specifications by the contractor.
...make a bid or proposal binding for the offerer while the customer has time to select among various bidders.

See references
Marked for review
 48. What should not be covered by a risk management plan?
Roles and responsibilities for handling project risks
Timing of project risk management activities
The methodological approach used for risk management
Individual risks and potential responses to them

See references
Marked for review
 49. You are assigned as the project manager to a project which had a on-time cost variance in the past caused by unexpected rework which has meanwhile been finished.

You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

EAC = 550,000
EAC = 525,000
EAC = 500,000
EAC = 425,000

See references
Marked for review
 50. An estimation has been made that the construction of a residential home will cost a certain amount per square foot of living area. This is an example of what type of estimating?
 
Analogous estimating
Bottom-up estimating
Top-down estimating
Parametric modeling

See references
Marked for review
 51. What is true for prototypes?
Prototyping causes significant costs and should be avoided wherever possible.
They are tangible and allow for early feedback on requirements by stakeholders.
Prototypes are mostly developed toward the end of a design or build phase.
Prototypes increase the risk of misunderstandings between developers and users.

See references
Marked for review
 52. What is a constructive change?
A change request that helps improving the project and its product, service or result and is discussed generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party considers an undocumented change to the contract.
A field change or ad-hoc change mandated by the project customer in a public construction project.
A change request which will lead to the re-construction of an older version of the project performance baseline by the contractor.

See references
Marked for review
 53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?
 
Working conditions and interpersonal relations
Responsibility for enlarged task
Interest in the task
Recognition for achievement

See references
Marked for review
 54. What is true for modern project management? Project managers need...
 
... to have a strict standing in negotiating
... to show experience in tricking business partners
... to be team players and facilitators instead of "bosses"
... to be strongly linked to local traditions

See references
Marked for review
 55. You are the project manager in an engineering project and have recently signed a contract with a software vendor for the development of a complicated control solution. The software will be used to control machinery equipment which your project team is currently developing. The contract is a lump-sum contract. The contractor has target cost estimated which seem rather low to you. Which of the following statements is not true for this situation?

It is the contractor's risk in this type of contract that their profit may vanish if costs have been underestimated.
This form of contract should only be chosen when all the requirements for the building of the product are well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time and extra costs for the changes to be applied.
It is likely that your organization may have to assume any unexpected additional costs for the software development.

See references
Marked for review
 56.

A review to determine whether of project activities comply with organizational and project policies, processes, and procedures is commonly called
 

Quality auditing
Inspection
Quality testing
Reject screening

See references
Marked for review
 57. Which of the following is true in regard to the Code of Accounts?
 
It allows one to easily identify the breakdown level of the item in the resource structure.
It describes the coding structure used by the performing organization to report financial information in its general ledger.
It is the collection of unique identifiers generally assigned to WBS items.
It defines ethical behavior in the project and the responsibilities to the customer and the profession.

See references
Marked for review
 58. You are the manager of your company's project management office. The company is running many concurrent projects; most of them share a resource pool of technical staff. Understanding how resources are utilized across projects has been found essential to overall project performance, including cost effectiveness and profitability.

This morning you received a message that the resource pool members will be unable to perform as planned for the next months because the overall work load has grown too high and while delays are adding up, the morale of the staff is going down.

What should you do next?
 

Ensure that quantitative information for all projects is being made available in a uniform and reliable fashion and verify that the project management methodology is adhered to. Then consolidate the information to get an understanding of the problems related with the use of shared resources.
Implement an enterprise project management software solution which is able to  level the human resources across the various projects and which has the capability to model resource assignment on a percentage level thus optimizing resource utilization for the overall organization.
Do nothing related to the described problem unless you are explicitly requested by the organizations upper management. Supporting decision making on the level on which project portfolio management is done, is not the project management office's business.
Evaluate project management software which supports planning and scheduling across enterprise-wide project portfolios. Avoid managing the availability of shared enterprise resources for the projects run by an organization because this is not the business of a project management office.

See references
Marked for review
 59.

You have been criticized that certain specifications in your Scope Statement do not pass the test for SMART objectives. What are SMART objectives?
 

Objectives specified in far more detail than necessary for a execution of a successful project.
Easily achievable objectives which help you reducing the pressure on yourself and the team.
Objectives that should be achieved in order to attain formal recognition by both the customer and the project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and time-related specifications.

See references
Marked for review
 60. You have been assigned as a project manager to a software project. While you and your team are working on a WBS (Work breakdown structure), estimations for activity durations based on the activity list vary significantly. Which additional documents may help you clarify this situation?

Milestone list and scope baseline.
Project schedule network diagrams and human resource plan.
Activity cost estimates and scope baseline.
Activity attributes and project scope statement.

See references
Marked for review
 61. You are performing Earned value technique on your project.

After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the remaining duration of the project, costs will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at Completion)?
 

EaC = BaC - CV
EaC = BaC / CPI
EaC = AC + BtC / CV
You can not compute the EaC.

See references
Marked for review
 62. During a company event, you had the opportunity to talk to a colleague project manager. He told you that in his current project actual costs are 15% under cumulated costs budgeted for today.

What do you think?

The information given to you by the colleague is not sufficient to assess project performance.
The project will probably be completed with total costs remaining under budget until the end.
A significant cost increase during the further course of the project will probably bring the costs back to baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow this variance.

See references
Marked for review
 63. What is the meaning of a concept called the "Journey to Abilene"?